What is time arrangement for HZQD900t beam launcher for tunnel?
In the bridge construction, it will help us a lot to control the project progress by learning time arrangement for passing tunnel of HZQD900t.
| Working  | Time arrangement | Remark  | |
| 1 | Check   all mechanisms of the beam launcher, prepare for passing tunnel by   disassembling it | 0.5 day | 
 | 
| 2 | Install   inner sleeve for worksite shift and make it stand on rear girder carrier | 0.5 day | 
 | 
| 3 | Dismantle   rear support leg, fold its upper and lower part, the main girder moves   backward | 1.5 days | 
 | 
| 4 | Dismantle   middle support leg, the main girder moves backward | 0.5 day | 
 | 
| 5 | Fix middle   support leg on girder transporter, front support leg draws back to the   condition for passing tunnel | 0.5 day | 
 | 
| 6 | Lower   down the beam launcher and carry it with girder transporter for passing   tunnel | 1 day | 
 | 
| 7 | Rotate the front support leg down to stand on the pier, put down   lower part of rear support leg, middle support leg supporting on girder   transporter draws back, jack up the complete machine | 0.5 day | 
 | 
| 8 | The complete   machine moves longitudinally, connect inner guide pillar of middle support   leg with bolts at lower part and stand on the road bed | 0.5 day | 
 | 
| 9 | Draw back the front support leg, and move it to front roadbed and   support | 0.5 day | 
 | 
| 10 | The complete machine moves to position where the middle support   leg could be assembled | 0.5 day | 
 | 
| 11 | Assemble rear support leg, rotate the middle support leg, rear   support leg moves to the position for girder installation | 1 day | 
 | 
| 12 | Dismantle the support frame for worksite shift, girder transporter   carries precast girder in the precast yard for girder installation | 0.5 day | 
 | 
| 12 | Total  | 8 day | 
 | 