What’re the Commissioning of Gantry Crane?
(A) Visual inspection of gantry crane:
1、Preparations and check:
(1)Turndown the whole circuit, ensure the installation meet the requirements.
(2)Check the following parts:
a、If the steel structure become deformed, welding seam crack.
b、To refuel the lubrication point.
c、The whole running gear move flexible.
d、Fasteners solid connection.
e、Qualified gear connection;
f、Acceptable brake installation.
g、No obstacle for crane moving.
h、Whether the steel rope intersect or knot. The rope length coincide with the lifting height.
(3)Electrical appliance:
a、Check the circuit and insulation resistance of electrical appliance
b, Check the wiring connection after cutting power.
c, Check the motor wiring connection.
d, Check the outdoor electronic component