How to Install Honeycomb Girder Gantry Crane?

Honeycomb girder gantry crane is made up of crane moving system, gantry mounting, operating cab, main longitudinal girder, walking platform, lifting trolley and electric hoist and etc.

1. Preparation for Installation of honeycomb girder gantry crane

Before installation of honeycomb girder gantry crane, it is necessary to be familiar with drawing and technical data.

2. Assembly sequence of honeycomb girder gantry crane:

main girder connection ----- outrigger ------ pull rod of outrigger ------ driven wheel box ------ adjust track gauge ------ driving wheel gauge ------ lifting trolley ------ operation cab ------ electrical system ------ safety inspection ------ testing run

3. During installation of honeycomb girder gantry crane:

At first, fix walking wheel box, outrigger and upper transverse girder on the track with steel pin, measure and align, tense mooring rope, then lift both ends of main girder slowly with two lifting cranes, lower it on outrigger and fasten it. In the same way, lift the other main girder and fix it , then use one crane to lift connection frame, lifting trolley, ladder, platform and guardrail, switch on all the electric circuit. After that, the assembly procedure is finished.

 