How to install rails of launching girder?
Launching girder can move longitudinally and laterally on the rail. Whether the launching girder works well to a large extent depends on quality of rail installation. If the installation is unqualified, chewing rails and collapsing is likely to occur in the moving process, which has a great effect on normal operation of launching girder.
Generally speaking, there are two ways to install runway track of rails: one is concrete precast girder, the other is steel girder. Built-in holes are a must for bolts connection in concrete precast girder, or embedded bolts in girder.
Ways to install rails of launching girder include pressing plate fixing method, hook-type screw fixing method, welding and bolts fixing method and other methods. For adjustment to the horizontal direction, long holes are usually made in the rail pressing plates; washer adding below the rail is for adjustment to vertical direction. Rail pressing plate must have enough stiffness as designing it, every pressing plate can be made with single or double holes according to load-bearing condition. The bumping block can be welded on the rail unless welding method is used for rail and runway track or fixed base steel plate on the runway track.
ZZHZ supply launching girders with various types. From product design to fabrication to installation and commissioning, our engineers will be there to give you a best proposal.