l        1、installing technology of overhead cranedouble girder overhead crane

l        crane rail installing-----crane traveling mechanism and lifting trolley assembly on the ground------bridge frame assembly on the ground-----bridge frame and crane traveling mechanism assembly on the  ground------bridge frame hoisting-----lifting trolley hoisting -----electrical system and other auxiliary facilities hoisting.

l        2、main hoisting machine and tools

l        under the  factory is not capped,according to the structure and  design of 20t overhead crane drawing, adopting a 80t truck crane hoists the crane in order.

l        The calculation of 80t truck crane lifting capacity:

l        In the project, the max.liftng capacity of 20t overhead crane is 23t, choosing a 80t truck crane to hoist, the turning radius of 80t truck crane is 5.5m.the arm length is 24m and the max.lifting capacity is 29.2t.

l        The safety factor of truck crane:0.8

l        The safety lifting capacity of truck crane:29.2×0. 8=23.36t

l        Truck crane safety lifting capacity:23.36t>23t

l        it can meet the safety hoisting need.。