What’re the preparations and check of 450t gantry crane?
(1)Turndown the whole circuit, ensure the installation of gantry crane meet the requirements.
(2)Check the following parts:
a、If the steel structure become deformed, welding seam crack.
b、To refuel the lubrication point.
c、The whole running gear move flexible.
d、Fasteners solid connection.
e、Qualified gear connection;
f、Acceptable brake installation.
g、No obstacle for crane moving.
h、Whether the steel rope intersect or knot. The rope length coincide with the lifting height.
(3)Ground connection requirements:
a、Reliable electrical connection is needed for the steel structure.
b、Check the circuit and insulation resistance of electrical appliance
c, Check the wiring connection after cutting power.