Organizational labor division of large-duty bridge girder launcher

One shift operating personnel labor division:

Field manager: 1 person (the leader can be the manager), command and coordinate the work on the front and rear abutmentlarge-duty bridge girder launcher

Field manager: 2 persons, one for front abutment, one for rear abutment

Front abutment: front support leg and auxiliary leg, command the guide beam to cross piers by moving longitudinally and put the girder in the right place

Rear abutment: rear support leg work shift, rail layout on the bridge deck, command the complete machine to cross piers, feed girders, move girders and drop girders

Leader: 1 person, be responsible for comprehensive work of the bridge girder launcher, scheduling the workers and ensuring and coordinating the normal work of the bridge girder launcher

Equipment maintenance engineer: 2 persons, one for electrical control, one for mechanical hydraulic section

Operator: 2 persons, one for main control room (with maintenance), one for power generation (also work as electrician)

Girder carrier driver: 1 person (also maintain the bridge girder launcher)

Hanging beam overhead crane supervisor: 4 persons (also maintain the machine)

Lifting workers: 7-10 workers (3-4 workers at the front part, 4-6 workers at the rear part)

Support crew: 2 support persons, one person for logistics service and carry and manage the labor and materials